A marine construction company shared more of its plans for a former industrial site near Connecticut’s shoreline. 

Its initial proposal for a large excavation operation had already faced some opposition. 

NBC Connecticut Chief Investigator Len Besthoff learned the company also wanted to use another part of the riverfront property to store unwanted fill and material from dredging operations. 

The property sits in the Gales Ferry section of Ledyard, across the Thames River from Uncasville. 

Gales Ferry Intermodal, a subsidiary of the Massachusetts-based Cashman marine construction firm, has been working on plans to develop the 165-acre property since purchasing it four years earlier. 

The first project Gales Ferry Intermodal proposed involves setting up an excavation operation. 

Town leaders voted it down, principally due to environmental concerns, and the company is suing the town. 

The case was scheduled for Hartford civil court this month. 

Gales Ferry Intermodal also went before a wetlands board in Ledyard recently to propose what it wanted to do with another part of the site. 

An attorney and a set of experts for Cashman explained that its subsidiary wanted to put non-hazardous fill and dredging material in two different places that made up just under 13 acres of the property. 

Environmental scientist George Logan said, “It is my professional opinion that the proposed regulated activities will not result in significant or adverse impacts to Allyn’s Pond, or Luna Pond, or the adjacent emerging wetlands.” 

People from Gales Ferry had concerns about the plan because part of the land used to have heavy industry and contained a brownfield. 

Sam Osborne of Ledyard said, “For you to make a decision for or against, I would highly recommend you work to find equivalent experts to just do a review.” 

The attorney for Gales Ferry Intermodal said this kind of operation was common, and the work would have been part of a large-scale pilot program with the state. 

We asked the state for confirmation of that and we’re waiting to hear back. 

Espace publicitaire · 300×250